Paving Complete At Darlington Raceway
Paving at Darlington Raceway began in mid-January, took nearly 15,000 tons of asphalt to complete and replaced a surface that was laid in 1994. Construction crews utilized 4 million reference points around the legendary track to ensure that the transitions in the corners and banking stayed true to the track’s original design.
The new racing surface was part of a $10 million capital improvement project that also included an infield access tunnel large enough to accommodate car haulers, motor homes and emergency vehicles and the addition of SAFER barrier walls to interior concrete walls on the frontstretch and backstretch.
"All of the upgrades that we have completed during this capital improvement project will play a vital role in the future of Darlington Raceway," said Browning.