Daytona Repave Update: Project Reaches The Halfway Mark
· Demolition of the old asphalt in Turns 1 and 2 began on Friday
· Paving on the skid pad extension continues
· Milling of asphalt on the apron on the Superstretch
· Work on paving the wearing course in Turns 3 and 4, through the start/finish line to the entrance of Turn 1 remains ongoing.
Lane Construction, which repaved other ISC race tracks will use an estimated 50,000 tons of asphalt to repave more than 1.4 million square feet of Daytona International Speedway and has a target completion date of Jan. 1, 2011. Race fans can view the progression of the historic repaving project from a section of the Oldfield Grandstands, which will open free to the public. Track tours will also be available through attraction admission to Daytona 500 Experience. For tickets and more information on Daytona International Speedway events, visit www.daytonainternationalspeedway.com or call 1-800-PITSHOP. DIS PR