DAYTONA Rising December Project Update
Fans can get an early preview of DAYTONA Rising during Budweiser Speedweeks 2015 (the stadium will officially open in 2016). Approximately 40,000 new seats will be available along with two of the five injectors/entrances, new concessions, several of the neighborhoods or social areas and the new vertical transportation.
Key DAYTONA Rising Accomplishments to Date:
• Installed more than:
o 470,000 bolts
o 90,000 square feet of metal panel skin
o 20,000 tons of structural steel and miscellaneous metals
Upcoming Race-Ready Activities:
• Install temporary Americrown kitchens and miscellaneous trailers
• Prepare vertical transportation for final testing
• Set up more than 4,000 feet of construction fencing